E-REDES builds new Medium Voltage line in Castelo Branco

An investment of 86 thousand euros, that aims to reinforce the quality of service in the area.

A new 30 kV Medium Voltage (MV) overhead line came into service, connecting two existing MV lines in the parish of Sarzedas, municipality of Castelo Branco.

This new interconnection, promoted by E-REDES, will increase the network's capacity and resilience, allowing for the improvement of service quality in the area.

For the construction of this new line, which took about a month, the company's teams also installed 11 medium voltage poles, which support about 1.9 kilometres of the new overhead line.

E-REDES thus continues to invest and innovate in the modernization of its infrastructure, in order to optimize its services and contribute to the development of the regions.