When you make a power connection request, you must support the initial process charges so that it advances:
INITIAL CHARGES FOR THE POWER CONNECTION PROCESS
Cost of connection Services
These services may include:
the Travel to the site to assess the tracing, connection point and power reception;
the Studies for the elaboration of bonding conditions;
the Preparation of budget network connection;
the Monitoring, supervision and reception of the work.
These costs are fixed by the energy services regulatory body and updated annually. They do not include the cost of drawing up the electricity project, which is the responsibility of those who request the connection when necessary.
Co-participation in power network
These costs are fixed by the energy services regulatory entity, updated annually, and depend solely on the requested power.
You can simulate the cost of the network connection budget via this link or refer to the links Manual
After this payment you will receive your budget within 15 working days.
POWER CONNECTION BUDGET
The budget of E-REDES will present the conditions of connection, the deadlines for execution, the information on the dimensions and technical characteristics of the connection and characterization of the materials to be used.
In this budget you will be aware of the possible connection options and the costs to support:
Costs with exclusive-use power network elements
They relate to costs incurred only with the connection of the premise concerned.
These costs will be borne by the requester up to the length of 30 meters of cable.
It is the responsibility of those who request the power connection for the execution of the network elements of exclusive use, using technicians or companies with competences for this purpose.
Costs with shared-use power network elements, if applicable
This type of cost occurs when there is the connection of one or more facilities and is calculated according to the requested power, distance and connection typology (aerial or underground).
These prices are defined by the Energy Services regulatory body and updated annually.
Other charges, if applicable:
the Licensing fees for connection elements to be built;
the Values arising from the issuance of opinions, licenses or guarantees that are necessary for the same purpose;
the Compensation of land owners traversed by the lines;
the Fees for permits for road crossings, railroad.
These charges may not be part of the initial budget and be billed later, before the end of the work.
Note: We advise that the budget initially presented by E-REDES may be altered in particular in cases where the originally planned network layout has to be revised by facts not attributable to E-REDES.