Renewable Energy
EU-SysFlex
Goals
- Characterize the needs of an electricity system with high penetration of renewables (> 50%);
- Optimize the coordination of flexibility (centralized and distributed) in European transport and distribution networks;
- Validate, in real environments, the tools that lead to the improvement of the operation of the distribution system operator and transport network;
- Conceptualize a market for the efficient integration of flexibility resources and study of impacts within the existing and future regulatory framework;
- Develop a "roadmap of flexibility", including replicability and scalability studies of solutions.
E-REDES scope
E-REDES is leading the Flexibility Hub, defining the user requirements and implementing the demo to validate the flexibility services delivered by the Distribution System Operator (DSO) to the Transmission System Operator (TSO), such as:
- Control of resources owned by the DSO for voltage control purposes and congestion management, reactive/active power ratio forecast and control;
- Technical validation of market flexibility activated by the TSO (including the virtual power plant (VPP));
- Dynamic equivalents for the transmission network nodes.
Project ID
Led by: Eirgrid |34 partners & 14 countries | Funded under: H2020-EU.3.3.4. | Grant Agreement ID: 773505
Start Date: November 2017
Finish Date: February 2022
Budget: €26,489,895.25
Learn more: https://eu-sysflex.com/