The power supply shall start after:
• grid connection implementation;
• settlement of grid connection cost;
• delivery of the work for which the applicant is responsible, where applicable;
• installation of metering equipment;
• authorisation from the land owners crossed by the power line;
• transfer to E-REDES of the plot of land where the switching station is located, where applicable;
• licensing, surveying and authorisation of the coming onstream by the Directorate-General for Energy and Geology (DGEG) of:
o the premise of the applicant;
o the grid connection infrastructure.
• the signing of an operating protocol;
• inspection of the interconnection protections, if any;
• electricity supply contract with a supplier.